Set it in place. Put it to work.
Our portable bridges are designed to be installed without a complicated construction process. Heavy-duty lifting rings, reinforced panels and tapered ends make them easy to unload, move and set, using equipment already found on many farms, logging sites and industrial properties.
Move your bridge from site to site as needed, or leave it in place for long-term or permanent access.
Preparing the crossing
Successful bridge support depends on the ground conditions at your site.
Common support surfaces include:
- Precast concrete blocks
- Timber or crane mats
- Rock-filled gabion baskets
- Crushed stone pads
- Suitable native ground
Each end of the bridge typically needs at least 5 feet of solid contact with the supporting surface. For example, a standard 60-foot bridge is commonly used to cover a 50-foot opening, leaving approximately 5 feet of support at each end.
Every property is different. The landowner or contractor should evaluate the banks and ground before installation and determine whether additional site preparation or engineering is needed.
Delivery and site access
Preparing the Route
Depending on its size and weight, the bridge may arrive stacked on one flatbed truck or divided between two trucks. Before delivery, make sure the truck and installation equipment have enough room to reach the crossing, turn around and unload safely.
It helps to confirm:
- The truck access route
- The unloading and staging area
- Overhead power lines and tree clearance
- Soft, steep or unstable ground
- Equipment reach and lifting capacity
A little preparation before the truck arrives can save a lot of wrestling once the steel is on site.
Unloading and Moving the Panels
Each bridge panel includes heavy-duty D-rings at both ends and four additional D-rings on top. These are the proper attachment points for lifting the panel with a crane, telehandler or excavator.
The panels can also be skidded or dragged into position one at a time. Care should be taken to protect the connection beams, pins and boxes while the panels are being moved.
Never Lift a Bridge Panel by the Guardrail
The guardrails are built to protect people on the bridge. They are not lifting points.
Connecting the bridge sections
Installation starts with the center bridge panel.
Once the center panel is properly positioned on the prepared supports, the two outside panels are lowered into place over the connecting-kit pins. These pins hold the sections in position while the bridge is connected and secured.
The crew should check that:
- Each panel is facing the correct direction
- The panel ends are lined up
- Both ends have solid bearing contact
- Connection parts are protected and properly seated
- The full bridge is level and stable before use
For bridges with heavy connection beams, the numbered panels are set in order. Installation begins with the middle crossbeam and works outward toward both ends. Grease is applied to help the tightly fitted beams slide through the connection boxes.
heavy connection kit
standard connection kit
Building the approaches
Once the bridge is set, ramps are commonly built at both ends to create a seamless transition from the road, trail or work area onto the bridge deck.
Typical ramp materials include:
- Compacted soil
- Graded aggregate
- Crane mats
- Wood chips
- Mulch
For longer-term installations, soil and stone approaches may also be finished with asphalt.
The right material depends on the equipment using the bridge, the amount of traffic and how long the bridge will remain in place.
Work Safe from the start
Bridge installation involves heavy equipment, suspended steel and changing ground conditions.
Everyone on site should use proper PPE, including steel-toe boots, hard hats, gloves and safety vests. The crew should also identify unstable ground, overhead lines, nearby trees and the location of other workers and equipment before lifting begins.
Clear communication matters. No guessing around suspended steel.
Important Installation Information
This page provides general educational information. Site conditions, ground stability, equipment and bridge use vary. Property owners and contractors are responsible for evaluating their site, choosing appropriate supports and following applicable safety and installation requirements.
See it in Action
Our modular bridge system goes from delivery to operational in one to two days. Designed for rapid deployment, durability, and versatility, our bridges are the ideal solution for both temporary access and permanent installations.